... average construction costs more than doubled in constant dollars during the 1970's and are expected to increase by another 80 percent for plants now under construction . Some of this increase has come from new regu- latory requirements ...
... average construction costs more than doubled in constant dollars during the 1970's and are expected to increase by another 80 percent for plants now under construction . Some of this increase has come from new regu- latory requirements ...
الصفحة 15
... Average nuclear plant construction leadtimes . doubled over the decade ( from about 60 to about 120 months ) and are now about 40 percent long- er than coal plant leadtimes . Very long leadtimes increase interest costs and the ...
... Average nuclear plant construction leadtimes . doubled over the decade ( from about 60 to about 120 months ) and are now about 40 percent long- er than coal plant leadtimes . Very long leadtimes increase interest costs and the ...
الصفحة 28
... Average Utility Stock Has Sold Below its Book Value . Implications for Federal Policies Chapter 3 References . Tables Table No. 49 Page 13. In 1970 , a Majority of Utilities Were Rated AA or Better ; in 1982 , a Majority Are Rated A or ...
... Average Utility Stock Has Sold Below its Book Value . Implications for Federal Policies Chapter 3 References . Tables Table No. 49 Page 13. In 1970 , a Majority of Utilities Were Rated AA or Better ; in 1982 , a Majority Are Rated A or ...
الصفحة 30
... Average annual 74 growth rate ( % ) 75 700 projecting 10 years 76 1974-7.6 1975 6.9 650 1976 - 6.4 1977 5.7 1978 5.2 1979 4.7 600 1980 4.0 1981 3.4 1982 3.0 550 1983 2.8 500 450 400 350 300 11111 Actual 77 78 79 80 81 82 83 74 75 76 77 ...
... Average annual 74 growth rate ( % ) 75 700 projecting 10 years 76 1974-7.6 1975 6.9 650 1976 - 6.4 1977 5.7 1978 5.2 1979 4.7 600 1980 4.0 1981 3.4 1982 3.0 550 1983 2.8 500 450 400 350 300 11111 Actual 77 78 79 80 81 82 83 74 75 76 77 ...
الصفحة 31
... average of 40 to 50 percent fewer months than for a nuclear plant ( 1 ) . Looking ahead , the prospects for substantial numbers of new central station powerplants ap- pear fairly uncertain . The prospects for more nuclear plants appear ...
... average of 40 to 50 percent fewer months than for a nuclear plant ( 1 ) . Looking ahead , the prospects for substantial numbers of new central station powerplants ap- pear fairly uncertain . The prospects for more nuclear plants appear ...
طبعات أخرى - عرض جميع المقتطفات
عبارات ومصطلحات مألوفة
accident at Three analysis Atomic Atomic Industrial Forum average backfits capacity factor capital cost changes chapter coal plants cogeneration commercial Commission components concerns construction costs coolant core CWIP decay heat developed discussed dollars economic elec Electric Utility electricity demand electricity prices engineering environmental estimates Federal fission fuel future growth rates hearings heat HTGR impact improve increase inflation INPO Institute ities leadtimes less licensing Light Water Reactors load Maine Yankee major ment nuclear energy nuclear industry nuclear plants nuclear power nuclear reactors Nuclear Regulatory Commission nuclear units option percent Photo credit powerplants pressurized water reactor problems projects proposed rate base rate regulation reac reduce regulatory reliability requirements risk safe safety issues SOURCE standards steam Strategy struction technical Three Mile Island tion tricity U.S. Nuclear uncertainty utility management vendors
مقاطع مشهورة
الصفحة 154 - ... provide adequate protection to the health and safety of the public.
الصفحة 172 - Individual members of the public should be provided a level of protection from the consequences of nuclear power plant operation such that individuals bear no significant additional risk to life and health.
الصفحة 8 - Administrator to the House Committee on Science and Technology and the Senate Committee on Energy and Natural Resources upon the request of either such committee.
الصفحة 91 - PWR steam generators have shown evidence of corrosion-induced wastage, cracking, reduction in tube diameter, and vibration-induced fatigue cracks. The primary concern is the capability of degraded tubes to maintain their integrity during normal operation and under accident conditions with adequate safety margins.
الصفحة 77 - The Future of Electric Power in America: Economic Supply for Economic Growth," DOE/PE-0045, US Department of Energy, June 1983 (B).
الصفحة 173 - The risk to an average individual in the vicinity of a nuclear power plant of prompt fatalities that might result from reactor accidents should not exceed one-tenth of one percent (0.1 percent) of the sum of prompt fatality risks resulting from other accidents to which members of the US population are generally exposed.
الصفحة 78 - 8th Annual Review of Overall Reliability and Adequacy of the North American Bulk Power Systems
الصفحة 172 - Societal risks to life and health from nuclear power plant operation should be comparable to or less than the risks of generating electricity by viable competing technologies and should not be a significant addition to other societal risks.
الصفحة 285 - Load factor. Load factor is the ratio of the average load over a designated period of time to the connected load.